Week of May 11, 2025
CONSTRUCTION UPDATE Crew A  - Crews will be working on the sewer lateral lines on 300 East  between 500 North and 650 North . Crew B...
Scott Henriksen
2 days ago2 min read
7 views
0 comments


Week of May 4, 2025
CONSTRUCTION UPDATE Crew A - Crews will be finishing work on the sewer main lines on 300 East between 500 North and 650 North . When...
Scott Henriksen
May 22 min read
10 views
0 comments


Week of April 27, 2025
CONSTRUCTION UPDATE Crew A - Crews will be finishing work on the sewer main lines on 300 East between 500 North and 650 North . When...
Scott Henriksen
Apr 252 min read
11 views
0 comments


Week of April 11, 2025
CONSTRUCTION UPDATE Crew A  - Crews will be finishing work on the sewer lateral lines on  550 North. When they are finished on this...
Scott Henriksen
Apr 182 min read
50 views
0 comments


Week of April 11, 2025
CONSTRUCTION UPDATE Crew A  - Crews will be working on the sewer lateral lines on  550 North. When they are finished on this street,...
Scott Henriksen
Apr 111 min read
17 views
0 comments


Week of April 6, 2025
CONSTRUCTION UPDATE Crew A  - Crews will be working on the sewer lateral lines on 140 East  and the sewer main line on  550 North. Crew...
Scott Henriksen
Apr 41 min read
10 views
0 comments


Week of March 30, 2025
CONSTRUCTION UPDATE Crew A - Crews will be working on the sewer lateral lines on 140 East and the sewer main line on 550 North. Crew B...
Scott Henriksen
Mar 281 min read
19 views
0 comments


Week of March 23, 2025
CONSTRUCTION UPDATE Crew A Â - Crews will be working on the sewer main line on 140 East and 550 North. Crew B -Â Crews will be working on...
Scott Henriksen
Mar 211 min read
10 views
0 comments


Week of March 16, 2025
CONSTRUCTION UPDATE Crew A Â - Crews will be working on the sewer main line on 140 East and 550 North. Crew B -Â Crews will be working on...
Scott Henriksen
Mar 142 min read
8 views
0 comments


Week of March 9, 2025
CONSTRUCTION UPDATE Crew A - Crews will be digging bore pits for the sewer main line that will be bored under the yards on 140 East and...
Scott Henriksen
Mar 72 min read
19 views
0 comments


Week of March 2, 2025
CONSTRUCTION UPDATE Crew A - Crews will be digging bore pits for the sewer main line that will be bored under the yards on 140 East and...
Scott Henriksen
Feb 282 min read
12 views
0 comments


Week of February 23, 2025
CONSTRUCTION UPDATE Crew A Â - In about 2 weeks, crews will begin digging bore pits for the sewer main line that will be placed under the...
Scott Henriksen
Feb 212 min read
23 views
0 comments


Week of February 16, 2025
CONSTRUCTION UPDATE Crew A - Crews will begin digging bore pits for the sewer main line that will be placed under the yards on 140 East...
Scott Henriksen
Feb 142 min read
12 views
0 comments


Week of February 2, 2025
CONSTRUCTION UPDATE 300 South will be closed for the next couple of weeks. Access the City offices via 550 North Crew A Â - Crews will be...
Scott Henriksen
Jan 312 min read
25 views
0 comments


Week of January 26, 2025
CONSTRUCTION UPDATE Crew A  - Crews will be working on the sewer lateral line on 300 East  between 200 South and 300 South. After this...
Scott Henriksen
Jan 242 min read
15 views
0 comments


Week of January 19, 2025
Crews will be working on Martin Luther King Day, Monday, January 20, 2024 CONSTRUCTION UPDATE Crew A Â - Crews will be working on the...
Scott Henriksen
Jan 172 min read
15 views
0 comments


Week of January 5, 2025
CONSTRUCTION UPDATE Crew A  - Crews will be working on the sewer main line on 300 East  between 200 South and 300 South. Crew B - Crews...
Scott Henriksen
Jan 31 min read
23 views
0 comments


Week of December 22, 2024
Crews will not be working from mid-day on December 24 Â through December 29 CONSTRUCTION UPDATE Crew A Â - Crews will be cleaning up...
Scott Henriksen
Dec 20, 20241 min read
27 views
0 comments


Week of December 15, 2024
CONSTRUCTION UPDATE Crew A - Crews are placing the sewer main lines on 430 East and 480 East Between 100 North and 200 North. Crew B...
Scott Henriksen
Dec 11, 20241 min read
11 views
0 comments


Week of December 2, 2024
CONSTRUCTION UPDATE Crew A Â - Crews are placing the sewer main lines on 200 North between 430 East and 500 East. Crew B -Â Crews will be...
Scott Henriksen
Nov 29, 20242 min read
29 views
0 comments