Week of June 29, 2025

  • Scott Henriksen
  • Jun 27
  • 1 min read

CREWS WILL NOT BE WORKING ON JULY 4 IN

OBSERVANCE OF INDEPENDENCE DAY


CONSTRUCTION UPDATE


Crew Assignments:

  • Crew A: Sprinkler repairs throughout town are ongoing.

  • Crew B: Repairing sidewalks and completing other concrete work throughout town.

  • Crew C: Installing lateral lines on 300 South (between 100 West and 100 East).

  • Crew D: Working on the sewer line on 100 West, between 100 North and 200 North. Work on 100 North, west of 100 West, is complete; however, this road will remain closed until work on 100 West is finished.

  • Crew E: Landscaping repairs, including backfilling lateral line trenches, will begin soon.


Important Note:

Lateral lines will run from the main sewer line to each property line. Homeowners are responsible for connecting their homes to the lateral line after sewer construction is completed.


ROAD CLOSURES


  • 100 North, between 50 West and 200 West, will be closed until late June

  • 100 West, between 200 South and 300 South, will be closed until late June

  • 300 South, between 100 West and Main Street, will be closed until lat June.



Please stay out of the construction zone. Do not drive on a closed road, unless you are trying to reach a house on that block.



 
 
 