Week of May 25, 2025
- Scott Henriksen
- May 23
- 2 min read
CONSTRUCTION UPDATE
Crew A – Preparing roads for asphalt paving; paving is expected to begin later this week.
Crew B – Repairing sprinklers and placing topsoil in lateral line trenches.
Crew C – Repairing sidewalks and other concrete work.
Crew D – Working on sewer lateral lines on 300 East, between 500 North and 650 North.
Crew E – Installing lateral lines on 200 South, between the Blacksmith Fork River and Main Street.
Crew F – Installing lateral lines on 300 South, between 100 West and 100 East.
Crew G – Working on the sewer line on 100 North, west of 100 West. This road will be closed during construction. All traffic to the High School and the seminary building should use 300 West or River Hawk Road. Once work on 100 North is complete, crews will begin work on 100 West, between 100 North and 200 North.
Lateral lines will run from the main line to the property line. Home owners will be responsible to connect their home to the lateral line after sewer construction is completed.
ROAD CLOSURES
300 East, north of 500 North, will be closed until the end of May
100 North, between 50 West and 200 West, will be closed until the end of May
200 South, between the river and Main Street will be closed until the end of May
300 South, between 100 West and 100 East, will be closed until the end of May
Main Street, between 250 South and 300 South, will be closed until early June.
Please stay out of the construction zone. Do not drive on a closed road, unless you are trying to reach a house on that block.

Comments