Week of August 3, 2025
- Scott Henriksen
- Aug 1
- 1 min read
CONSTRUCTION UPDATE
Crew Assignments
Crew A – Asphalt Preparation
Asphalt prep work continues citywide. We apologize for the paving delay and appreciate your patience. As previously shared, the schedule is dependent on material availability. Our supplier has indicated that the asphalt mix may be delayed by up to 10 additional days, which will affect paving timelines. We will share updated information as soon as it becomes available.
Crew B – Landscaping & Trench Backfill
Landscaping and backfilling of lateral trenches are ongoing in various locations throughout the city.
Important Note:
Lateral lines will extend from the main sewer line to each property's boundary. Once sewer construction is complete, homeowners are responsible for connecting their homes to the lateral line.