Week of June 15, 2025
- Scott Henriksen
- Jun 13
- 1 min read
CONSTRUCTION UPDATE
Nearly every road has been prepared for repaving. Please drive with extra caution in areas where asphalt has been removed.
Crew Assignments:
Crew A: Continuing asphalt paving throughout town
Crew B: Sprinkler repairs and topsoil placement in lateral line trenches are on hold until asphalt paving is complete.
Crew C: Repairing sidewalks and completing other concrete work.
Crew D: Installing lateral lines on 300 South (between 100 West and 100 East).
Crew E: Working on the sewer line on 100 West, between 100 North and 200 North.
Crew F: Installing a sewer lateral on 100 North, west of 100 West. This road will be closed during construction. All traffic to the high school and the seminary building should use 300 West or Riverhawk Drive.
Important Note:
Lateral lines will run from the main sewer line to each property line. Homeowners are responsible for connecting their homes to the lateral line after sewer construction is completed.
ROAD CLOSURES
100 North, between 50 West and 200 West, will be closed until mid June
100 West, between 200 South and 300 South, will be closed until mid June
300 South, between 100 West and Main Street, will be closed until mid June.
Please stay out of the construction zone. Do not drive on a closed road, unless you are trying to reach a house on that block.