CONSTRUCTION UPDATE

Nearly every road has been prepared for repaving. Please drive with extra caution in areas where asphalt has been removed.


Crew Assignments:

  • Crew A: Asphalt paving has begun on the south end of town. Crews will work from south to north.

  • Crew B: Repairing sprinklers and placing topsoil in lateral line trenches.

  • Crew C: Repairing sidewalks and performing other concrete work.

  • Crew D: Working on sewer lateral lines on 600 North, east of 300 East.

  • Crew E: Installing lateral lines on 300 South (between 100 West and 100 East), and on 100 West (south of 200 South).

  • Crew F: Working on the sewer line on 100 North, west of 100 West. This road will be closed during construction. All traffic to the high school and the seminary building should use 300 West or Riverhawk Drive. Once work on 100 North is complete, crews will begin work on 100 West, between 100 North and 200 North.


Important Note:

Lateral lines will run from the main sewer line to each property line. Homeowners are responsible for connecting their homes to the lateral line after sewer construction is completed.


ROAD CLOSURES


  • 100 North, between 50 West and 200 West, will be closed until mid June

  • 100 West, between 200 South and 300 South, will be closed until mid June

  • 300 South, between 100 West and Main Street, will be closed until mid June.

  • Main Street, between 250 South and 300 South, will be closed until early June.


Please stay out of the construction zone. Do not drive on a closed road, unless you are trying to reach a house on that block.



 
 
 