Crew A – Asphalt Preparation
Asphalt paving will continue throughout the week. The crew will remain on site until all roadway paving is complete.
Crew B – Landscaping and Trench Backfill
Landscaping, sprinkler repairs, and trench backfilling are ongoing at various project locations.
Crew C – Chip Seal
Chip sealing on Highway 165 is scheduled for Thursday and Friday. 2600 South and 2900 South/100 South will be closed to all traffic. High school traffic should enter from 300 West or 100 North.
Public Notice
Residents and motorists should use caution near active construction areas. Please follow posted traffic signs and watch for workers and equipment.
Important Note
Lateral lines will extend from the main sewer line to each property boundary. Once sewer construction is complete, homeowners are responsible for connecting their homes to the lateral line.