Week of September 19, 2025
- Scott Henriksen
- Sep 19
- 1 min read
CONSTRUCTION UPDATE
Crew A – General Cleanup
Over the next two weeks, crews will be completing general cleanup and finishing topsoil placement in the project area.
Crew B – 2600 South Sewer Work
Starting September 29, crews will begin switching Ridgeline High School from the Logan sewer system to the new Millville system. This work is expected to take about two weeks.
We appreciate your patience and cooperation as these improvements are completed.
Public Notice
Residents and motorists should use caution near active construction areas. Please follow posted traffic signs and watch for workers and equipment.
Important Note
Lateral lines will extend from the main sewer line to each property boundary. Once sewer construction is complete, homeowners are responsible for connecting their homes to the lateral line.