CONSTRUCTION UPDATE




Crew A – Asphalt Preparation

Asphalt paving is scheduled to begin on August 18. The crew is expected to remain in town until all roads are completed.


Crew B – Landscaping & Trench Backfill

Landscaping, sprinkler repair, and backfilling of lateral trenches are ongoing at various locations. Crews are currently working in the Shire, on the north end of town, and will work south through town over the next few weeks.


Important Note:

Lateral lines will extend from the main sewer line to each property's boundary. Once sewer construction is complete, homeowners are responsible for connecting their homes to the lateral line.