Week of July 13, 2025
- Scott Henriksen
- Jul 11
- 1 min read
CONSTRUCTION UPDATE
Crew Assignments:
Crew A: Performing sidewalk repairs and other concrete work at various locations.
Crew B: Installing the main sewer line on 550 East, north of Center Street.
Crew C: Landscaping repairs, including backfilling lateral line trenches, will resume after asphalt paving is completed.
Important Note:
Lateral lines will extend from the main sewer line to each property's boundary. Once sewer construction is complete, homeowners are responsible for connecting their homes to the lateral line.
ROAD CLOSURES
550 East, north of Center Street, will be closed until mid July
Please stay out of the construction zone. Do not drive on a closed road, unless you are trying to reach a house on that block.