CONSTRUCTION UPDATE
Crew A - Crews will be working on the sewer lateral lines on 300 East between 500 North and 650 North.
Crew B - Crews will be working on the lateral lines on 200 South, between the Blacksmith Fork River and Main Street.
Crew C - Crews will continue work on 265 South. When they are done on 265 South, they will finish the lateral line work on 100 West, between 200 South and 300 South
Crew D - Crews will be working on the lateral lines on 300 South, between 100 West and 100 East.
Crew E - Crews will be working on the sewer line on 100 North, west of 100 West; this road will be closed while they complete this work. All traffic going to the High School and the seminary building will need to come from 300 West or River Hawk Road. When they are done on 100 North, they will begin work on 100 West between 100 North and 200 North.
Lateral lines will run from the main line to the property line. Home owners will be responsible to connect their home to the lateral line after sewer construction is completed.
ROAD CLOSURES
300 East, north of 500 North, will be closed until the end of May
100 North, between 50 West and 200 West, will be closed until the end of May
200 South, between the rive and Main Street will be closed until the end of May
300 South, between 100 West and 100 East, will be closed until the end of May
265 South will be closed until the end of May
Please stay out of the construction zone. Do not drive on a closed road, unless you are trying to reach a house on that block.