CONSTRUCTION UPDATE


Crew Assignments:

  • Crew A: Asphalt repairs citywide, focusing on 600 North and 300 East this week.

  • Crew B: Installing sewer lateral on 550 East, north of Center Street.

  • Crew C: Landscaping and backfilling lateral trenches resumes Monday, starting in the Mondair area and continuing to other locations citywide.


Important Note:

Lateral lines will extend from the main sewer line to each property's boundary. Once sewer construction is complete, homeowners are responsible for connecting their homes to the lateral line.


ROAD CLOSURES


  • 550 East, north of Center Street, will be closed until late July


Please stay out of the construction zone. Do not drive on a closed road, unless you are trying to reach a house on that block.