Week of June 23, 2024
CONSTRUCTION UPDATE Crew A - Crews are working on the pressurized sewer line on Highway 165. They are currently working between 2900...
Scott Henriksen
Jun 21, 20242 min read


Week of June 16, 2024
CONSTRUCTION UPDATE Crew A - Crews are working on the pressurized sewer line on Highway 165. They are currently working between 2900...
Scott Henriksen
Jun 14, 20242 min read


Week of June 9, 2024
CONSTRUCTION UPDATE Crew A - Crews are preparing to start work on the pressurized sewer line on Highway 165. This work will be done via...
Scott Henriksen
Jun 7, 20242 min read


Week of June 2, 2024
**Be aware that this schedule is subject to last minute modifications and changes. CONSTRUCTION UPDATE Crew A - Crews are preparing to...
Scott Henriksen
May 31, 20242 min read


Week of May 26, 2024
CREWS WILL NOT BE WORKING ON MONDAY MAY 27, in observance of Memorial Day. CONSTRUCTION UPDATE Crew A - Crews are finishing up work on...
Scott Henriksen
May 24, 20242 min read


Week of May 19, 2024
CONSTRUCTION UPDATE Crew A - Crews will be working on both the sewer lift station, just west of the Blacksmith Fork River on 2900 South,...
Scott Henriksen
May 17, 20242 min read


Week of May 12, 2024
CONSTRUCTION UPDATE Crew A - Crews are focusing their work on the **sewer lift station** just west of the Blacksmith Fork River on 2900...
Scott Henriksen
May 10, 20242 min read


Week of May 5, 2024
CONSTRUCTION UPDATE Crew A - Crews are focusing their work on the sewer lift station just west of the Blacksmith Fork River on 2900...
Scott Henriksen
May 3, 20242 min read


Week of April 28, 2024
CONSTRUCTION UPDATE Crew A - Crews are focusing their work on the sewer lift station just west of the Blacksmith Fork River on 2900...
Scott Henriksen
Apr 26, 20242 min read


Week of April 21, 2024
CONSTRUCTION UPDATE Crew A - Crews are focusing their work on the sewer lift station just west of the Blacksmith Fork River on 2900...
Scott Henriksen
Apr 19, 20242 min read


Week of April 15, 2024
CONSTRUCTION UPDATE Crew A - Crews are focusing their work on the sewer lift station just west of the Blacksmith Fork River on 2900...
Scott Henriksen
Apr 12, 20242 min read


Week of April 8, 2024
CONSTRUCTION UPDATE Crew A - Crews are focusing their work on the sewer lift station just west of the Blacksmith Fork River on 2900...
Scott Henriksen
Apr 5, 20242 min read


Week of March 31, 2024
CONSTRUCTION UPDATE Crew A - Crews are focusing their work on the sewer lift station just west of the Blacksmith Fork River on 2900...
Scott Henriksen
Mar 29, 20242 min read


Week of March 24, 2023
CONSTRUCTION UPDATE Crew A - Crews are focusing their work on the sewer lift station, just west of the Blacksmith Fork River on 2900...
Scott Henriksen
Mar 22, 20242 min read


Week of March 17, 2023
CONSTRUCTION UPDATE Crew A - Crews are focusing their work on the sewer lift station, just west of the Black Smith Fork River on 2900...
Scott Henriksen
Mar 15, 20242 min read


Week of March 10, 2023
CONSTRUCTION UPDATE Crew A - Crews are focusing their work on the sewer lift station, just west of the Black Smith Fork River on 2900...
Scott Henriksen
Mar 8, 20242 min read


March 3 - March 10
CONSTUCTION UPDATE Crew A - Crews are focusing their work on the sewer lift station, just west of the Black Smith Fork River on 2900...
Scott Henriksen
Mar 2, 20242 min read


Week of February 25, 2024
CONSTRUCTION UPDATE Crew A - Crews are focusing their work on the sewer lift station, just west of the Black Smith Fork River on 2900...
Scott Henriksen
Feb 23, 20242 min read


Week of February 18-24
CONSTRUCTION UPDATE Crew A - Crews are finishing work on the sewer line that runs through the field, on the north side of 100 South at...
Scott Henriksen
Feb 16, 20242 min read


Week of February 11 thru February 17
CONTRUCTION UPDATE Crew A - Crews continue work on the sewer line that runs through the field, on the north side of 100 South at...
Scott Henriksen
Feb 9, 20242 min read