Week of February 25, 2024

Scott Henriksen

CONSTRUCTION UPDATE

  • Crew A - Crews are focusing their work on the sewer lift station, just west of the Black Smith Fork River on 2900 South.

  • Crew B - Crews will continue to work on 300 North between 100 East and 200 East. This area will be closed to through traffic while this work is being completed. Once they have completed the work on this road, the crew will continue east on 300 North between 200 East and 300 East.

  • Crew C - Crews are working on 100 West between 200 South and 300 South. Once they complete work on 100 West this crew will turn the corner, and eastward on 300 South.

  • Crew D - Crews have begun work on 100 East between 200 North and 300 North. Once they are done in this area they will begin work on Main Street between 200 North and 300 North

  • Crew E - Crews are now working 500 North between 200 East and 300 East. This crew will be in this area for approximately 2 weeks. Once they are done on 500 North, they will be moving the 250 East between 500 North and 600 North

  • Crew F - Crews are continuing work on Main Street between 100 South and 200 South.

  • Crew G - Crews are continuing lateral line connections on 100 South between Main Street and 100 East. This work is expected to last approximately 2 weeks.

**Lateral lines will run from the main line to the property line. Home owners will be responsible to connect their home to the lateral line after sewer construction is completed.**



ROAD CLOSURES

  • 500 North, between 200 East and 300 East, will be closed from mid-February to early March.

  • 300 North, between 100 East and 200 East, will be closed until early March.

  • 100 South, between Main Street and 100 East, will be closed from mid-February to the beginning of March

  • 100 East, between 200 North and 300 North, will be closed until early March

  • Main Street, between 100 South and 200 South, will be closed for approximately 1 more week

  • 100 West, between 200 South and 300 South, will be closed from February 12 to first week of March.


 
 
 