CONSTRUCTION UPDATE
Crew A - Crews are focusing their work on the sewer lift station just west of the Blacksmith Fork River on 2900 South.
Crew B - Crews will be working on the sewer main line on 300 East* between 350 North and 400 North. This area will be closed to through traffic while work is being completed. Once they have completed the work on this road, the crew will move to 350 East between 300 East and 350 East.
Crew C - Crews are placing the sewer lateral lines on 200 North between 150 East and 200 East.
Crew D - Crews will be boring the sewer lines along the Highway 165 around 4400 South. The bulk of this work will be in the shoulders. Expect some traffic shifts.
Crew E - Crews are working on the sewer lateral lines on 100 North between 100 West and Main Street. Once they are done on this road, they will be moving to 200 North between 200 West and Main Street.
Crew F - Crews continue to work on the sewer main line on 300 South between Main Street and 100 East. There has been a slight change to their plans, once they get to 100 East, they will continue east on 300 South.
Sewer work on Highway 165 will start in May. Much of this work will be done via lateral boring. Traffic control and road closures will be shifting frequently. Be extra cautious as driving between Millville and Hyrum.
ROAD CLOSURES
500 North, between 100 East and 200 East will be closed from mid-April to the early May
350 North, between 300 East and 350 East will be closed from late-April to early May
300 East , between 350 North and 450 North will be closed from late-April to the end of April
100 North, between 100 West and Main will be closed until the end of April
200 North, between 200 West and Main will be closed until the middle of May
200 North, between 100 East and 300 East, will be closed until the middle of May
300 South, between Main Street and 200 East, will be closed until the mid-May
Please stay out of the construction zone. Do not drive on a closed road, unless you are trying to reach a house on that block.