CONSTRUCTION UPDATE
Crew A - Crews are focusing their work on the sewer lift station, just west of the Black Smith Fork River on 2900 South.
Crew B - Crews will be finishing the sewer mainline on 300 North between 200 East and 300 East. This area will be closed to through traffic while work is being completed. Once they have completed the work on this road, the crew will to 250 East/250 North just south of 300 North.
Crew C - Crews have begun the sewer line work on 300 South. They are currently working between 100 West and Main Street. They will be working their way eastward on 300 South over the next 4-6 weeks.
Crew D - Crews are placing the sewer lateral lines on 100 East between 200 North and 300 North.
Crew E - Crews are placing the sewer lateral lines on 100 South between 100 East and 200 East.
Crew F - Crews are beginning construction of the sewer mainline on 100 West between 100 South and 200 South.
Crew G - Crews are placing the sewer mainline on 100 East between 100 South and 200 South. Once they have completed the mainline, they will place the lateral service lines in this same area.
Lateral lines will run from the main line to the property line. Homeowners will be responsible to connect their home to the lateral line after sewer construction is completed.

ROAD CLOSURES
200 East, between 500 North and 600 North, will be closed from mid-March to late-March.
300 North, between 200 East and 300 East, will be closed until mid-March.
250 East/250 North, will be closed from Mid March to late March.
200 North, between 100 East and 300 East, will be closed until mid-March.
100 South, between 100 East and 200 East, will be closed from mid-March
100 East, between 200 North and 300 North, will be closed until mid-March
100 East, between 100 South and 200 South, will be closed until mid-March
100 West, between 100 South and 200 South, will be closed until mid-March
300 South, between 100 west and Main Street, will be closed until mid-March