Week of May 12, 2024

CONSTRUCTION UPDATE


  • Crew A - Crews are focusing their work on the **sewer lift station** just west of the Blacksmith Fork River on 2900 South.

  • Crew B - Crews will be working on the sewer main line on **350 East** between 250 North and 350 North. This area will be closed to through traffic while work is being completed. Once they have completed the work on this road, the crew will begin lateral line connections on 350 East and 350 North.

  • Crew C - Crews are placing the sewer lateral lines on **200 North** between 200 East and 300 East. Once they are done on 200 North, this crew will begin lateral connection work on 200 East, between 100 North and 250 North

  • Crew D - Crews will be boring the sewer lines along the **Highway 165** around 4400 South. The bulk of this work will be in the shoulders. Expect some traffic shifts.

  • Crew E - Crews are working on clean up and repairs in the middle section of town. These repairs will include sprinkler lines and irrigation ditches.

  • Crew F - Crews continue to work on the sewer main line on **300 South** between 100 East and 200 East.


Sewer work on Highway 165 will start in May. Much of this work will be done via lateral boring. Traffic control and road closures will be shifting frequently. Be extra cautious as driving between Millville and Hyrum.


Lateral lines will run from the main line to the property line. Home owners will be responsible to connect their home to the lateral line after sewer construction is completed.




ROAD CLOSURES


  • 500 North, between 200 East and 300 East will be closed from mid-April to the early May

  • 350 North, between 300 East and 350 East will be closed from mid-May to late May

  • 350 East, between 350 North and 300 North will be closed from early May to the mid-May

  • 200 East, between 100 North and 250 East, will be closed until the middle of May

  • 200 North, between 200 East and 300 East, will be closed until the middle of May

  • 300 South, between 100 East and 200 East, will be closed until the mid-May


Please stay out of the construction zone. Do not drive on a closed road, unless you are trying to reach a house on that block.