CONSTRUCTION UPDATE

  • Crew A - Crews are focusing their work on the sewer lift station just west of the Blacksmith Fork River on 2900 South.

  • Crew B - Crews will be working on the sewer main line on 250 East between 350 North and 400 North. This area will be closed to through traffic while work is being completed. Once they have completed the work on this road, the crew will move to 300 East between 350 East and 450 East.

  • Crew C - Crews are placing the sewer lateral lines on 200 North between 100 East and 200 East.

  • Crew D - Crews will be preparing for sewer main work on Highway 165. They will be digging bore holes over the next few weeks.

  • Crew E - Crews are working on the sewer lateral lines on 100 North between 100 West and Main Street.

  • Crew F - Crews continue to work on the sewer main line on 300 South between Main Street and 100 East. Once they are done with this section, they plan to turn south on 100 East.


Sewer work on Highway 165 will start in May. Much of this work will be done via lateral boring. Traffic control and road closures will be shifting frequently. Be extra cautious as driving between Millville and Hyrum.

Lateral lines will run from the main line to the property line. Home owners will be responsible to connect their home to the lateral line after sewer construction is completed.




ROAD CLOSURES


  • 500 North, between 100 East and 200 East will be closed from mid-April to the end of April

  • 350 North, between 200 East and 300 East will be closed from mid-April to the end of April

  • 250 East, between 350 North and North, will be closed next week

  • Center Street, between 100 West and Main will be closed until the end of April

  • 200 North, between Main Street and 200 East, will be closed until the end of April

  • 100 East, between 100 South and Center, will be closed until the end of April

  • 100 West, between 100 South and 200 South, will be closed from the end of April to May

  • 300 South, between 100 west and 100 East, will be closed until the mid-May


Please stay out of the construction zone. Do not drive on a closed road, unless you are trying to reach a house on that block.