CONSTUCTION UPDATE
Crew A - Crews are focusing their work on the sewer lift station, just west of the Black Smith Fork River on 2900 South.
Crew B - Crews will continue to work on 300 North between 200 East and 300 East. This area will be closed to through traffic while this work is being completed. Once they have completed the work on this road, the crew will to 250 East just south of 300 North
Crew C - Crews are working on 100 West between 200 South and 300 South. Once they complete work on 100 West this crew will turn the corner, and eastward on 300 South.
Crew D - Crews will continue work on 100 East between 200 North and 300 North. Once they are done in this area, this crew will begin placing lateral sewer connections on 200 North between Main Street and 300 East.
Crew E - Crews are now working on 500 North between 200 East and 300 East. This crew will be in this area for approximately 2 weeks. Once they are done on 500 North, they will be moving to 250 East between 500 North and 600 North
Crew F - Crews are continuing work on 100 East between 100 South and 200 South. Once they are done in this area they will begin work on 100 West between 100 North and Center St.
Crew G - Crews are continuing lateral line connections on 100 South between 100 E and 200 East. This work is expected to last approximately 2 weeks.
Lateral lines will run from the main line to the property line. Homeowners will be responsible to connect their home to the lateral line after sewer construction is completed.
ROAD CLOSURES
500 North, between 200 East and 300 East, will be closed from mid-February to early March.
300 North, between 200 East and 300 East, will be closed until mid-March.
100 South, between 100 East and 200 East, will be closed from mid-March
100 East, between 200 North and 300 North, will be closed until early March
100 West, between 200 South and 300 South, will be closed until mid-March
100 West, between 100 North and Center, will be closed until mid-March