CONTRUCTION UPDATE
Crew A - Crews continue work on the sewer line that runs through the field, on the north side of 100 South at approximately 175 West. This crew will also be working on the sewer lift station, just west of the Black Smith Fork River, on 2900 South.
Crew B - Crews will continue to work on 300 North, between Main Street and 100 East. This area will be closed to through-traffic while this work is being completed. Once they have complete the work on this road, the crew will continue up 300 North, between 100 East and 200 East.
Crew C - Crews are finishing work on 200 South, between 100 East and 160 East. Once they are done in this area, they will be moving to 100 West, between 200 South and 300 South.
Crew D - Crews are working in the area between 200 East and 300 East. This area will be closed for approximately 1 week. After crews have complete the work on this road, they will begin work on 100 East, between 200 North and 300 North.
Crew E - Crews will continue to work on 500 North between 100 East and 200 East, once they are done with this block, they will continue on 510 North, up to 300 East. This crew will be in this area for approximately 3 weeks.
Crew F - Crews have begun work on Main Street, between 100 South and 200 South.
ROAD CLOSURES
500 North, between 100 East and 200 East, will be closed from January 26 to mid-February.
300 North, between Main Street and 100 North, will be closed until mid-February.
200 East, between 200 North and 300 North, will be closed for approximately 1 more week.
Main Street, between 100 South and 200 South, will be closed for approximately 1 more week
100 West, between 200 South and 300 South, will be closed from February 12 to first week of March.