CONSTRUCTION UPDATE
Crew A - Crews are preparing to start work on the pressurized sewer line on Highway 165. This work will be done via lateral boring. Crews will be digging bore pits approximately every 1000 feet to accommodate the boring equipment. There will be minimal traffic shifts around the bore pit areas.
Crew C - Crews are placing the sewer main line on Main Street between Center Street and 100 North. Once this crew is done on Main Street, they will be turning east on Center and work eastward.
Crew D - Crews will be boring the sewer lines along the Highway 165 around 4400 South. The bulk of this work will be in the shoulders. Expect some traffic shifts.
Crew F - Crews will be working on the lateral line connections on 500 North between 200 East and 300 East. When this crew is done on 500 North, they will begin the lateral connection work on 250 East, between 500 North and 600 North. These areas will be closed to through traffic while work is being completed.
Lateral lines will run from the main line to the property line. Home owners will be responsible to connect their home to the lateral line after sewer construction is completed.
ROAD CLOSURES
500 North, between 200 East and 300 East will be closed until early June
300 North, between 200 East and 300 East will be closed from late May to mid-June
250 East/250North, will be closed from late May to mid-June
200 East, between 250 North and 300 North will be closed from late May to mid-June
Main Street, between Center Street 100 North will be closed until the early June
Please stay out of the construction zone. Do not drive on a closed road, unless you are trying to reach a house on that block.