Week of February 18-24

CONSTRUCTION UPDATE

  • Crew A - Crews are finishing work on the sewer line that runs through the field, on the north side of 100 South at approximately 175 West. Upon completion of the section, this crew will focus their work on the sewer lift station, just west of the Black Smith Fork River on 2900 South.

  • Crew B - Crews will continue to work on 300 North between Main Street and 100 East. This area will be closed to through traffic while this work is being completed. Once they have completed the work on this road, the crew will continue up 300 North, between 100 East and 200 East.

  • Crew C - Crews expect to complete work on 200 South between 100 East and 160 East, this week. Once they are done in this area, they will be moving to 100 West, between 200 South and 300 South.

  • Crew D - Crews will continue work on 200 East, between 200 North and 300 North. This area will be closed for approximately 1 week. After crews have completed the work on this road, they will begin work on 100 East, between 200 North and 300 North.

  • Crew E - Crews will continue to work on 500 North between 100 East and 200 East. Once they are done with this block, they will continue on 510 North up to 300 East. This crew will be in this area for approximately 3 weeks.

  • Crew F - Crews are continuing work on Main Street between 100 South and 200 South.

  • Crew G - Crews will begin lateral line connections on 200 North between 150 West and Main Street.** This work is expected to last approximately 2 weeks.

  • Crew H - Crews will begin lateral line connections on 100 North between 100 West and Main Street.** This work is expected to last approximately 2 weeks.

  • Crew I - Crews will begin lateral line connections on 100 South between Main Street and 100 East.** This work is expected to last approximately 2 weeks.

**Lateral lines will run from the main line to the property line. Home owners will be responsible to connect their home to the lateral line after sewer construction is completed.**



ROAD CLOSURES

  • 500 North, between 100 East and 200 East, will be closed from January 26 to mid-February.

  • 300 North, between Main Street and 100 East, will be closed until mid-February.

  • 200 North, between Main Street and 100 West, will be closed from mid-February to the beginning of March

  • 100 North, between Main Street and 100 West, will be closed from mid-February to the beginning of March

  • 100 South, between Main Street and 100 East, will be closed from mid-February to the beginning of March

  • 200 East, between 200 North and 300 North, will be closed for approximately 1 more week.

  • 100 East, between 200 North and 300 North, will be closed for after 200 North is reopend. This closure will last for approximately 3 weeks.

  • Main Street, between 100 South and 200 South, will be closed for approximately 1 more week

  • 100 West, between 200 South and 300 South, will be closed from February 12 to first week of March.


27 views0 comments