CONSTRUCTION UPDATE
Concrete repair for curb, gutter, and sidewalk repairs is ongoing. This work is expected to last 3-4 weeks.
Crews will be doing asphalt repair on Highway 165 through out this week. Asphalt repairs in Millville will resume on October 17.
Crew A - Crews are preparing areas around town for concrete and paving.
Crew B - Crews will be working on the lateral lines on 600 North between 120 East and 200 East. This area will be closed to through traffic while work is being completed.
Crew C - Crews are placing the sewer lateral lines on 100 East between 100 North and Center Street.
Crew D - This crew will be doing lateral line repairs throughout town.
Crew F - Crews will be working on the sewer main line on 100 North, between 380 East and 500 East. This road will be closed to through traffic while work is being completed.
Lateral lines will run from the main line to the property line. Home owners will be responsible to connect their home to the lateral line after sewer construction is completed.
ROAD CLOSURES
600 North between 120 East and 200 East will be closed until late August
100 East between Center Street and 100 North will be closed until late-September
100 North between 380 East and 500 East will be closed until mid-October
100 South / 2900 South will be closed between Highway 165 and the river until the end of October.
Please stay out of the construction zone. Do not drive on a closed road, unless you are trying to reach a house on that block.