Week of October 6, 2024

Scott Henriksen

CONSTRUCTION UPDATE

  • Concrete repair for curb, gutter, and sidewalk repairs is ongoing. This work is expected to last 3-4 weeks.

  • Crews will be doing asphalt in town on Monday and Tuesday. Crews will return the week on October 14.

  • Crew A - Crews are placing the sewer lateral lines on 350 East between 200 North and 250 North.

  • Crew B - Crews will be working on the lateral lines on 600 North between 120 East and 200 East. This area will be closed to through traffic while work is being completed. After work on 600 North is complete, this crew will be moving to 200 South to work on lateral lines between 100 East and 300 East.

  • Crew C - Crews are placing the sewer lateral lines on 200 North between 100 West and Main Street.

  • Crew D - This crew will be doing lateral line repairs throughout town.

  • Crew F - Crews will be working on the sewer main line on 100 North, between 380 East and 500 East. This road will be closed to through traffic while work is being completed.

Lateral lines will run from the main line to the property line. Home owners will be responsible to connect their home to the lateral line after sewer construction is completed.





ROAD CLOSURES


  • 600 North between 120 East and 200 East will be closed until late August

  • 200 North between 100 West and Main Street will be closed until mid-October

  • 100 North between 380 East and 500 East will be closed until mid-October

  • 100 South / 2900 South will be closed between Highway 165 and the river until the end of October.


Please stay out of the construction zone. Do not drive on a closed road, unless you are trying to reach a house on that block.