CONSTRUCTION UPDATE
Concrete repair for curb, gutter, and sidewalk repairs is ongoing. This work is expected to continue through the end of the month.
Asphalt paving will resume. They will be focusing their efforts on 500 North, Main Street, 200 North, 350 North, the dugway, and 100 East south of 300 South.
Crew A - Crews are placing the sewer main lines on 470 East between 200 North and 100 North.
Crew B - Crews will be working on the lateral lines on 200 South between 100 East and 300 East.
Crew C - Crews are placing the sewer lateral lines on 100 North up the dugway.
Crew D - This crew will be doing lateral line repairs throughout town.
Crew F - Crews will be working on the sewer main line on 400 East, between 100 North and 25 North. This road will be closed to through traffic while work is being completed.
Crew G - Crews are placing the sewer lateral lines on 200 North west of 100 West.
Crew H - Crews are repairing the sewer main lines on 200 West between 100 South and 200 South.
Lateral lines will run from the main line to the property line. Home owners will be responsible to connect their home to the lateral line after sewer construction is completed.

ROAD CLOSURES
200 West between 100 South and 200 South will be closed until the end of October
200 North west of 100 West will be closed until the end of October
100 North between 380 East and 500 East will be closed until mid-October
100 South / 2900 South will be closed between Highway 165 and the river until the end of October.
The dugway will be closed until the end of October
400 East, between 100 North and 25 North will be closed until the end of October.
470 East, between 100 North and 25 North will be closed until the end of October.
Please stay out of the construction zone. Do not drive on a closed road, unless you are trying to reach a house on that block.