Crews will not be working November 28 and 29 in observance of the Thanksgiving Holiday
CONSTRUCTION UPDATE
Crew A - Crews are placing the sewer main lines on 200 North between 380 East and 500 East.
Crew B - Crews will be working on the lateral lines on 350 South between 100 East and 200 East, as well as on 200 East south of 300 South
Crew C - Crews will be working on the sewer main line on 300 South between 300 East and 500 East. This road will be closed to through traffic.
Crew D - Crews are placing the sewer lateral lines on 380 East between 100 North and 25 North.
Crew E - Crews are repairing the sewer main lines on 200 West between 100 South and 200 South. When they are done on this road they will move to 100 West between 100 South and 200 South.
Crew F - Crews are placing sewer lateral lines on 200 East between 100 North and 200 North.
Crew G - Crews are working on the lift station. However, 2900 South is open to traffic.
Lateral lines will run from the main line to the property line. Home owners will be responsible to connect their home to the lateral line after sewer construction is completed.
ROAD CLOSURES
200 West between 100 South and 200 South will be closed until the end of November.
200 North between 380 East and 500 East will be closed until the end of November.
300 South between 200 East and 500 East will remain closed until the end of November.
300 South between 100 East and 200 East will remain closed until the end of November.
200 East between 100 North and 200 North will be closed until the end of November.
380 East between 200 North and 100 North will be closed until the end of November.
Please stay out of the construction zone. Do not drive on a closed road, unless you are trying to reach a house on that block.