Week of May 4, 2025

  • Scott Henriksen
  • May 2
  • 2 min read

CONSTRUCTION UPDATE


  • Crew A - Crews will be finishing work on the sewer main lines on 300 East between 500 North and 650 North. When they are done with the main line work, they will then do the lateral line work in these same areas.

  • Crew B - Crews will be working on the sewer lateral lines on Main Street, between 150 South and 300 North.

  • Lateral line work on Main Street, in front of the elementary school, is expected to begin the week of May 5. For the safety of the children, crews will stop work from 8:30-9:00 am, and 3:30-3:45 pm Monday through Thursday, and 2:25-2:30 pm on Friday.

  • Please arrange with your children to pick them up on Center Street or 100 South while this work is taking place

  • Crew C - Crews will be working on the water line on Center Street, east of 200 East.

  • Crew D - Crews will be finishing work on the lateral lines on 100 East, between 200 South and 300 South. When they are done on this street, this crew will begin work on the sewer main line on Main Street, between 250 South and 300 South.

  • Crew E - Crews will begin work on 100 North, west of 100 West the week of May 12th. This road will be closed while they complete this work.

  • All traffic going to the High School and Seminary will need to come from 300 West or River Hawk Road.


Lateral lines will run from the main line to the property line. Home owners will be responsible to connect their home to the lateral line after sewer construction is completed.


ROAD CLOSURES


  • Main Street, in various locations through the middle of May

  • 300 East, north of 500 North, will be closed until mid May

  • 100 North, west of 100 West, will be closed beginning the week of May 5

  • Center Street, east of 200 East, will be closed until late April


Please stay out of the construction zone. Do not drive on a closed road, unless you are trying to reach a house on that block.




 
 
 

Recent Posts

See All
Week of May 11, 2025

CONSTRUCTION UPDATE Crew A   - Crews will be working on the sewer lateral lines on 300 East  between 500 North and 650 North . Crew B...

 
 
 