Week of July 7, 2024

CONSTRUCTION UPDATE


  • Crew A - Crews are working on the pressurized sewer line on Highway 165. They are currently working between 3200 South and 3600 South. This work is being done via lateral boring. Crews will be digging bore pits approximately every 1000 feet to accommodate the boring equipment. There will be minimal traffic shifts around the bore pit areas. They expect to be working in this area until the end of July.

  • Crew B - Crews will be working on lateral line connections on 400 North between 100 West and 100 East. This area will be closed to through traffic while work is being completed. They will also be working on 100 East, near 300 North

  • Crew C - Crews are placing the sewer main line on Center Street between 100 East and 200 East. As they finish this area they will continue to work eastward on Center Street.

  • Crew D - Crews will be working on the lift station and begin prepping for the crossing of the Black Smith Fork river.

  • Crew F - Crews will be working on the lateral line connections on 500 North between 250 East and 300 East. This area will be closed to through traffic while work is being completed. When they are done this crew will be moving to 200 East between 500 and 600 North

  • Crew G - Crews will be working on the sewer main line on 100 East, south of 300 South. Please access the south fields via 200 East then 350 South


Lateral lines will run from the main line to the property line. Home owners will be responsible to connect their home to the lateral line after sewer construction is completed.





ROAD CLOSURES


  • 200 East between 500 North and 600 North will be closed until mid to late July

  • 600 North between 100 East and 200 East will be closed until late July

  • 300 North between 100 West and100 East will be closed until mid-July

  • Center Street between 100 East and 200 East will be closed until the mid July

  • 100 East south of 300 South will be closed until late July

  • Highway 165 between 3200 South and 3600 South has a traffic lance shift. Please pay attention to the traffic control, as the work in the area is changing often.


Please stay out of the construction zone. Do not drive on a closed road, unless you are trying to reach a house on that block.