CONSTRUCTION UPDATE


  • Crew A - Crews will be working on the sewer lateral line on 300 East between 200 South and 300 South. After this crew has completed the work on 300 East they will relocate to 100 West, between 100 South and Center Street, to work on sewer lateral lines.

  • Crew B - Crews will be working on the sewer main line on 100 West between 200 South and 100 South. 200 South will be closed at 100 West until the end of next week.

  • Crew C - Crews are working on the sewer main line on Canyon Road. Access will be very restricted. There will be no canyon access until the end of February. Crews will work to accommodate traffic to this road, but it is recommended that residents park at the city park from 8:30 am - 5:30 p.m. daily.

  • Crew D - Crews will be working on the pressurized sewer line on 2900 South/100 South.

  • Crew E - Crews are placing sewer lateral lines in the Mondair neighborhood, on 25 South and 500 East.

  • Crew F - Crews will begin work on the sewer Main line on Center Street between 500 East and 600 East.


Lateral lines will run from the main line to the property line. Home owners will be responsible to connect their home to the lateral line after sewer construction is completed.



ROAD CLOSURES


  • Canyon Road will be closed until the end of February.

  • 100 West between Center and 200 South will be closed until mid-February



Please stay out of the construction zone. Do not drive on a closed road, unless you are trying to reach a house on that block.