Week of January 22, 2023

CONSTRUCTION UPDATE

  • Crew A - Crews will begin work on the sewer line that runs through the field, on the north side of 100 South at approximately 175 West. This work is expected to begin on Monday, January 22. 100 South will be closed between 100 West and 200 West for approximately 1 week.

  • Crew B - Crews are continuing work on 400 North between Main and 120 East. This area will be closed to through-traffic while this work is being completed. Once they have complete the work on this road, the crew will begin work on 100 East between 300 North and 400 North.

  • Crew C - Crews are continuing to work on 200 South. They are moving to the area between Main Street and 100 East on Monday, January 15. This area will be closed for approximately 2 more weeks.

  • Crew D - Crews continue to work on 200 North. They are moving to the area between 200 East and 300 East on Monday, January 15. This area will be closed for approximately 2 more weeks. Once they have complete the work on this road, the crew will begin work on 200 East between 200 North and 300 North.

  • Crew E - Crews will be working on 100 East, between 450 North and 500 North. Once they complete the work on this road the crew will begin work on 500 North between 100 East and 200 East.


ROAD CLOSURE

  • 450 North, between Main Street and 100 East, will be closed from January 22 to the end of January.

  • 400 North, between Main Street and 100 East, will be closed from January 2 to the end ofJanuary.

  • 200 North, between 200 East and 300 East, will be closed for approximately 3 more weeks

  • 100 South will be closed between 100 West and 200 West for a week beginning January 22.

  • 100 East, north of 450 North will be closed to non-local traffic. This closure is expected to last 2 weeks. ALL traffic will need to use 200 East as an alternate route.