CONSTRUCTION UPDATE

300 South will be closed for the next couple of weeks. Access the City offices via 550 North

  • Crew A - Crews will be working on the sewer lateral line on 300 South between 200 East and 550 East.

  • Crew B - Crews will be working on the sewer lateral line on 100 West between 200 South and 300 South.

  • Crew C - Crews are working on the sewer main line on Canyon Road. Access will be very restricted. There will be no canyon access until the end of February. Crews will work to accommodate traffic to this road, but it is recommended that residents park at the city park from 8:30 am - 5:30 p.m. daily.

  • Crew D - Crews will be working on the pressurized sewer line on 2900 South/100 South.

  • Crew E - Crews are placing sewer lateral lines in the Mondair neighborhood, on 200 North, 430 East and 470 East.

  • Crew F - Crews will be working on the sewer lateral line on 100 West between Center Street and 100 South.


Lateral lines will run from the main line to the property line. Home owners will be responsible to connect their home to the lateral line after sewer construction is completed.


ROAD CLOSURES


  • 300 South between 200 East and 550 East will be closed until the end of February.

  • Canyon Road will be closed until the end of February.

  • 100 West between Center and 100 South, and 200 South and 300 South, will be closed until mid-February



Please stay out of the construction zone. Do not drive on a closed road, unless you are trying to reach a house on that block.