CONSTRUCTION UPDATE
Crew A - Crews will begin digging bore pits for the sewer main line that will be placed under the yards on 140 East and 550 North. Once they have completed digging the bore pits, crews will begin boring this sewer main line.
Crew B - Crews will be working on the sewer lateral line on 100 West between 200 South and 300 South. Once they are done on this street they will begin the sewer main line work on 265 South.
Crew C - Crews are working on the sewer lateral lines on Canyon Road. Access will be very restricted. There will be no canyon access until the end of February. Crews will work to accommodate traffic to this road, but it is recommended that residents park at the city park from 8:30 am - 5:30 p.m. daily.
Crew D - Crews are placing sewer lateral lines in the Mondair neighborhood, on 480 East. After they finish the lateral line work, they will begin sewer main line work on Center Street between 500 East and 600 East.
Crew E - Crews will be working on the sewer lateral line on 100 West between 100 South and 200 South. Once they finish on this street, the crew will begin lateral line work on 100 South between Main Street and 100 West. Traffic leaving the south parking lot at the school will have to turn east.
Lateral lines will run from the main line to the property line. Home owners will be responsible to connect their home to the lateral line after sewer construction is completed.

ROAD CLOSURES
100 South between 50 West and 100 West, until the end of Frebruary
100 West between Center and 100 South, and 200 South and 300 South, will be closed until end of February
Canyon Road will be closed until the end of February
Center Street, between 500 East and 600 East will be closed until the end of February. Traffic will not be able to cross Center Street on 550 East during this time.
Please stay out of the construction zone. Do not drive on a closed road, unless you are trying to reach a house on that block.