Week of December 22, 2024

  • Scott Henriksen
  • Dec 20, 2024
  • 1 min read

Crews will not be working from mid-day on December 24 through December 29


CONSTRUCTION UPDATE


  • Crew A - Crews will be cleaning up 430 East and 480 East.

  • Crew B - Crews will be working on the lateral lines on 350 South between 100 East and 200 East.

  • Crew C - Crews are working on the sewer main line on Canyon Road. Access will be very restricted to this road. There will be no canyon access until the end of February. Crews will work to accommodate traffic to this road, but it is recommended that residents park at the city park from 8:30 am - 5:30 p.m. daily.

  • Crew D - Crews are working on the lift station. However, 2900 South is open to traffic.

  • Crew E - Crews are placing sewer lateral lines on 300 East between 100 North and 200 North.


Lateral lines will run from the main line to the property line. Home owners will be responsible to connect their home to the lateral line after sewer construction is completed.





ROAD CLOSURES


  • Canyon Road will be closed until the end of February.

  • 350 South will be closed until the end of the year.

  • 300 East between 100 North and 200 North will be closed until the end of the year.


Please stay out of the construction zone. Do not drive on a closed road, unless you are trying to reach a house on that block.

 
 
 

Recent Posts

See All
Week of May 11, 2025

CONSTRUCTION UPDATE Crew A   - Crews will be working on the sewer lateral lines on 300 East  between 500 North and 650 North . Crew B...

 
 
 

Comments


Millville Sewer Line Project

©2022 by Jacques & Associates Inc.

bottom of page