CONSTRUCTION UPDATE
Crew A - Crews are placing the sewer main lines on 200 North between 430 East and 500 East.
Crew B - Crews will be working on the lateral lines on 350 South between 100 East and 200 East, as well as on 200 East south of 300 South
Crew C - Crews will be working on the sewer main line on 300 South between 300 East and 500 East. This road will be closed to through traffic.
Crew D - Crews are placing the sewer lateral lines on 380 East between 100 North and 25 North.
Crew E - Crews are working on the lift station. However, 2900 South is open to traffic.
Crew F - Crews are placing sewer lateral lines on 250 East between 150 North and 200 North. When they are done on 250 East, this crew will be moving to 300 East to place sewer lateral lines between 100 North and 200 North.
Lateral lines will run from the main line to the property line. Home owners will be responsible to connect their home to the lateral line after sewer construction is completed.
ROAD CLOSURES
200 North between 380 East and 500 East will be closed until early December.
300 South between 200 East and 500 East will remain closed until early December.
250 East between 100 North and 200 North will be closed until early December.
300 East between 100 North and 200 North will be closed until mid December.
380 East between 200 North and 100 North will be closed until early December.
Please stay out of the construction zone. Do not drive on a closed road, unless you are trying to reach a house on that block.