CONSTRUCTION UPDATE
Crew A - Crews are working on the pressurized sewer line on Highway 165. They are currently working between 3200 South and approximately 3400 South. This work is being done via lateral boring. Crews will be digging bore pits approximately every 1000 feet to accommodate the boring equipment. There will be minimal traffic shifts around the bore pit areas. They expect to be working in this area until the end of August.
Crew B - Crews will be working on lateral line connections on 450 North between Main Street and 300 East. This area will be closed to through traffic while work is being completed.
Crew C - Crews are placing the sewer main line on Center Street between 200 East and 300 East. When they finish this area they will begin sewer main line work on 100 East between 100 North and Center Street.
Crew D - Crews are continuing to working on the Sewer Lift station as well as working on the sewer crossing at the Black Smith Fork River just south of 2900 South/100 South. This area will be closed while this work is taking place.
Crew F - Crews will be working on the lateral line connections on 200 East between 450 and 600 North. This area will be closed to through traffic while work is being completed. When they are done on 200 East, they will begin to work on the lateral line connections on 600 North.
Crew G - Crews will be working on the sewer main line on 350 South, between 100 East and 200 East.
Lateral lines will run from the main line to the property line. Home owners will be responsible to connect their home to the lateral line after sewer construction is completed.
ROAD CLOSURES
200 East between 450 North and 600 North will be closed until early August
100 East Between 100 North and Center Street closed until the mid August
350 South between 100 East and 200 East will be closed until early August
200 East south of 300 South will be closed until mid-August
Main Street between 400 North and 400 North will be closed until mid-August
100 South/2900 South between Highway 165 and 200 West will be closed until mid August
Highway 165 between 3200 South and 3400 South has a traffic lance shift. Please pay attention to the traffic control, as the work in the area is changing often.
Please stay out of the construction zone. Do not drive on a closed road, unless you are trying to reach a house on that block.
Comments