Week of August 23, 2024

CONSTRUCTION UPDATE


  • Crew A - Crews are working on the pressurized sewer line on Highway 165. They are currently working between 3750 South and Johnson Road. This work is being done via lateral boring. Crews will be digging bore pits approximately every 1000 feet to accommodate the boring equipment. There will be minimal traffic shifts around the bore pit areas. Access from Highway 165 to Hollow Road will be closed this upcoming week. They expect to be working in this area until the early September.

  • Crew B - Crews will be working on lateral lines on 600 North between 120 East and 200 East. This area will be closed to through traffic while work is being completed. When they finish this area they will begin the lateral line work.

  • Crew C - Crews are placing the sewer lateral lines on Center Street between 100 East and 200 East. When they finish this area they will begin sewer main line work on 100 East between 100 North and Center Street.

  • Crew D - Crews are continuing to work on the Sewer Lift station as well as working on the sewer crossing at the Black Smith Fork River just south of 2900 South/100 South. This area will be closed while this work is taking place.

  • Crew F - Crews will be working on the sewer main line on 200 East south of 300 South. When they finish this area they will begin sewer main line work on the 150 East cul-de-sac, south of 350 South.

  • Crew G - Crews will be working on the sewer main line on Main Street between 100 North and 300 North. This area will be closed to through traffic while work is being completed.

  • Crew H - Crews will begin work on the sewer main line on the Dugway just east of the cemetery, between 100 North and 200 North. This road will be closed to through traffic while work is being completed. All traffic to Mondair will need to use alternate routes.


Lateral lines will run from the main line to the property line. Home owners will be responsible to connect their home to the lateral line after sewer construction is completed.






ROAD CLOSURES


  • 600 North between 120 East and 200 East will be closed until early September

  • 100 East between 100 North and Center Street closed until the end of August

  • 200 East south of 300 South will be closed until the end of August

  • The Dugway just east of the cemetery, between 100 North and 200 North will be closed until the end of September

  • Main Street between 100 North and 300 North will be closed until mid-August

  • 100 South/2900 South between Highway 165 and 200 West will be closed until end of August

  • Highway 165 between 3750 South and Johnson Road has a traffic lance shift. Please pay attention to the traffic control, as the work in the area is changing often.

  • Access from Highway 165 to Hollow Road will be closed this upcoming week


Please stay out of the construction zone. Do not drive on a closed road, unless you are trying to reach a house on that block.