CONSTRUCTION UPDATE

  • Crew A - Crews have begun work on the sewer line that runs through the field, on the north side of 100 South at approximately 175 West.

  • Crew B - Crews awill begin work on 100 East between 300 North and 400 North. This area will be closed to through-traffic while this work is being completed. Once they have complete the work on this road, the crew will begin work on 300 North, between Main Street and 100 East.

  • Crew C - Crews are continuing to work on 200 South. They are moving to the area between 100 East and 160 East. This area will be closed for approximately 2 weeks.

  • Crew D - Crews continue to work on 200 North. They are working in the area between 200 East and 300 East. This area will be closed for approximately 1 more week. Once they have complete the work on this road, the crew will begin work on 200 East between 200 North and 300 North.

  • Crew E - Crews have begun\work on 500 North between 100 East and 200 East, once they are done with this block, they will continue on 510 North, up to 300 East. This crew will be in this area for approximately 3 weeks.


ROAD CLOSURES

  • 500 North, between 100 East and 200 East, will be closed from January 26 to mid-February.

  • 300 East, between 300 North and 400 North, will be closed from January 30 to mid-February.

  • 200 North,*between 200 East and 300 East, will be closed for approximately 1 more week.

Please stay out of the construction zone. Do not drive on a closed road, unless you are trying to reach a house on that block.




 
 
 

Recent Posts

See All
Week of May 11, 2025

CONSTRUCTION UPDATE Crew A   - Crews will be working on the sewer lateral lines on 300 East  between 500 North and 650 North . Crew B...

 
 
 

Comentários


Millville Sewer Line Project

©2022 by Jacques & Associates Inc.

bottom of page