March Work Update

  • Writer: Rosie Fullmer
    Rosie Fullmer
  • Mar 7, 2023
  • 1 min read
  • Crews are currently working to lay sewer line pipe on 200 South between 200 South and 200 East. This work is expected to continue through the second week of March.

  • Crews continue to work at the railroad tracks in Hyrum to install sewer casing pipe and will continue to work here throughout the month. Flagging operations are in place.

Beginning March 13th

  • Construction crews will begin work on 200 East between 100 South and 200 South. This work is expected to continue in this area throughout March.



 
 
 