January 7 - January 14

CONSTRUCTION UPDATES

  • Crew A - Crews are continuing to work in Hyrum installing pipe near 4400 South, between 700 West and the highway. Once this work is complete in Hyrum, Crew A will begin running the sewer through the field, on the north side of 100 South at approximately 100 West.

  • Crew B - Crews will begin work on 400 North between Main and 100 East after the New Year. This area will be closed to through-traffic while this work is being completed.

  • Crew C - Crews are continuing to work on 200 South. 200 South is closed between 100 West and Main Street. This area will be closed for approximately 2 more weeks. After the new year, they will continue to work on 200 South and cross Main Street.

  • Crew D - Crews continue to work on 200 North between 100 East and 200 East.

  • Crew E - Crews will be working on the 250 East, just off of 450 North. This area will be closed for approximately 1 more week. After they finish work on 250 East, they will move to 150 North, just off of 450 North.


ROAD CLOSURES

  • 400 North, between Main Street and 100 East, will be closed from January 2- to mid-January.

  • 200 North, between 100 East and 200 East ,will be closed for approximately 3 more weeks

  • 100 South will be closed between 100 West and 200 West for a couple of days beginning mid January.

  • 200 South is closed between 100 West and Main Street. This closure is expected to last 1 week.

  • 250 East, off of 450 North will be closed to non-local traffic. This closure is expected to last 2 weeks. ALL traffic will need to use alternate routes.


Please stay out of the construction zone. Do not drive on a closed road, unless you are trying to reach a house on that block.