Crews will be working January 2. All crews will return January 3.
CONSTRUCTION UPDATE
Crew A - Crews will be working on the 250 East, just off of 450 North. This area will be closed for approximately 1 more week.
Crew B - Crews are continuing to work on 200 South. 200 South will be closed between 100 West and Main Street. This area will be closed for approximately 2 more weeks. After the new year, they will continue to work on 200 South and cross Main Street.
Crew C - Crews will be starting to work on 200 North between 100 East and 200 East.
Crew D - Crews will begin work on 400 North between Main and 100 East after the New Year. This area will be closed to through-traffic while this work is being completed.
Crew E - Crews are continuing to work in Hyrum installing pipe near 4400 South, between 700 West and the highway.
ROAD CLOSURES
200 North between 100 East and 200 East will be closed for approximately 3 more weeks
400 North* between Main Street and 100 East will be closed from January 2- to mid-January.
200 South is closed* between 100 West and Main Street. This closure is expected to last 1 weeks.
250 East, off of 450 North will be closed* to non-local traffic. This closure is expected to last 2 weeks. ALL traffic will need to use alternate routes.
Please stay out of the construction zone. Do not drive on a closed road, unless you are trying to reach a house on that block.