Crew A - Work on 100 South continues. Crews are currently between Main Street and 100 East. The work in this area is expected to take approximately 2 weeks, weather and staff dependent
Crew B - Work will begin on 550 North on Monday, June 26th. They will be working between 300 West and Main Street.
Crew C - Work on 100 North continues. Crews are currently between 100 East and 200 East. Crews will be placing the sewer line from this area all the way up to the cemetery. The work in this area is expected to take approximately 2 more weeks, weather and staff dependent. They will then continue east on 100 North.
Crew D - Work on the east side of Highway 165 will begin on Monday, June 26th. The initial work area will be between 2900 South and 2600 South. Crews will begin at 2900 South and work north towards 2600 South. This work is expected to take multiple months.
Crew E - Work in Hyrum will resume on July 3.

Road Closures
100 South is closed between Main Street and 100 East.
100 North is closed to through traffic between 100 East and 200 East.