Construction Update and Road Closures

  • Writer: Rosie Fullmer
    Rosie Fullmer
  • Jan 11, 2023
  • 1 min read

This week - Work has resumed at 100 South (west of 100 West). This work is expected to last until January 20th.



January 16th - Crews will begin working on 200 South (between 100 East and 200 East). This work is expected to take approximately 2 weeks.


January 23rd - Crews will continue working at the railroad tracks in Hyrum to install sewer casing. Crews will be working in this area for approximately 2 weeks.


ROAD CLOSED

100 South is closed to through traffic between 100 West and 200 West.


200 South will be closed beginning January 16th between Main St. and 100 East.


Schedules are subject to change due to weather conditions, material availability and other unforeseen circumstances.

 
 
 

Recent Posts

See All
Week of May 11, 2025

CONSTRUCTION UPDATE Crew A   - Crews will be working on the sewer lateral lines on 300 East  between 500 North and 650 North . Crew B...

 
 
 

Commentaires


Millville Sewer Line Project

©2022 by Jacques & Associates Inc.

bottom of page