Construction Update
Week of November 12th
▪Crew A - Crews will be in Hyrum installing pipe near 4400 South, between 700 West and the highway.
▪Crew B - Crews will begin work on 200 South and 200 West. 200 South will be closed between 100 West and the Highway. This area will be closed for approximately 3 weeks
▪Crew C - Crews will be working on 300 North between 150 West and Main Street
▪Crew D - Crews will be working on 100 East, between 100 North and 200 North.
ROAD CLOSURES
▪300 North between 150 West and Main Street will be closed for approximately 2 weeks▪100 East between 100 North and 200 North will be closed for approximately 2 weeks▪200 South will be closed between Highway 165 and 100 West beginning Monday November 6. This closure is expected to last 3 weeks. ALL traffic will need to use alternate routes to access the city.
Please stay out of the construction zone. Do not drive on a closed road, unless you are trying to reach a house on that block.