ROAD CLOSURES THIS WEEK AFFECT MILLVILLE ELEMENTARY ACCESS

Updated: Feb 9, 2023


This week:

  • Crews continue to work on 100 South between Main Street and 100 West. This work is expected to last until February 20th.

School drop-off on the south side of the school will be closed while this work is being done.

  • Crews are working on 200 South between 100 East and 200 East. This work is expected to take approximately 2 weeks.

  • Crews are continuing to work at the railroad tracks in Hyrum to install sewer casing pipe. Crews will be working in this area for the next 3 weeks. Flagging operations are in place.

February 20th:

  • Crews will begin working on 200 South between 200 East and 300 East.


ROAD CLOSURES

  • 100 South is closed to through traffic between 100 West and 200 West.

  • 200 South is closed to through traffic between 100 East and 200 East.

  • 100 South is closed to through traffic between Main Street and 100 West.

  • 1200 West in Hyrum is closed between 4300 South and 4700 South. Flag operations are in place.